1. Pre-Construction
• Lot selection
• Floor Plans and Specifications
• Subcontractor Bids and Agreements
• Financing
• Permits (5 days to 2 weeks)
2. Foundation
• Utilities
• Stake and Survey/Building Envelope
• Excavation
• Footings/Foundation
• Sub rough in Plumbing
• Inspections
3. Framing
• Thermal Envelope
• Rough in Plumbing
• Rough in Electrical
• Rough in HVAC
• Rough in Cable/Phone
• Inspections
• Lot selection
• Floor Plans and Specifications
• Subcontractor Bids and Agreements
• Financing
• Permits (5 days to 2 weeks)
2. Foundation
• Utilities
• Stake and Survey/Building Envelope
• Excavation
• Footings/Foundation
• Sub rough in Plumbing
• Inspections
3. Framing
• Thermal Envelope
• Rough in Plumbing
• Rough in Electrical
• Rough in HVAC
• Rough in Cable/Phone
• Inspections
4. Interior Work
• Insulation and Vapor Barrier
• Drywall
• Hardwood Floors
• Cabinets
• Trim
• Paint
5. Exterior Work
• Flat Concrete
• Gutters
• Caulking
• Paint
• Final Grade/Landscaping
• Sprinklers
•Sod
6. Finishes
• Ceramic/Brick
• Bath Accessories
• Plumbing/Electric/HVAC
• Carpet
• Punch List
• Final Clean
• Inspections/Certificate of Occupancy
• Insulation and Vapor Barrier
• Drywall
• Hardwood Floors
• Cabinets
• Trim
• Paint
5. Exterior Work
• Flat Concrete
• Gutters
• Caulking
• Paint
• Final Grade/Landscaping
• Sprinklers
•Sod
6. Finishes
• Ceramic/Brick
• Bath Accessories
• Plumbing/Electric/HVAC
• Carpet
• Punch List
• Final Clean
• Inspections/Certificate of Occupancy